We have lift off!!!

The house build has started......they actually started on August 28th and it is going up pretty quickly so about time we posted some pictures I think. BTW - I know we posted an example picture of the house we were building on the initial blog but thought I should mention our's will look different because our garage is on the right as you look it and of course will also have the garage set back from the front of the house due to the developer "design" rules.

Day 1 - we got a porta loo!!!



The view down the street, left out the front door



By Sept 11th we had a slab



By Sept 20th we had a frame and two very excited boys!!!








By Sept 27th we had some windows, scaffolding and guttering up and roof tiles.....on the ground!!!